Force Majeure Under FIDIC: From “Force Majeure” To “Exceptional Events” — What Changed and Why It Matters

Force Majeure Under FIDIC: From “Force Majeure” To “Exceptional Events” — What Changed and Why It Matters

CMGuide
CMGuideJun 12, 2026

Key Takeaways

  • 2017 FIDIC rebrands force majeure as “Exceptional Events” with tighter procedures
  • Notice within 14 days, then a full claim within 84 days
  • Cost recovery only for war, terrorism, contamination; natural disasters stay contractor risk
  • Immediate documentation—photos, diaries, expert reports—is essential under the 2017 regime

Pulse Analysis

The transition from force majeure to "Exceptional Events" in the 2017 FIDIC suite reflects a strategic move toward greater contractual precision. By embedding the relief mechanism within the overarching claims procedure, FIDIC forces parties to treat disruptions with the same rigor as any other claim. This integration raises the evidentiary bar: claimants must issue a notice within 14 days of awareness and follow up with a fully detailed claim in 84 days, mirroring the standard time‑and‑cost claim process. The result is a more predictable, albeit demanding, pathway for obtaining extensions of time.

A critical nuance lies in the allocation of financial risk. Both the 1999 and 2017 editions grant time extensions for all qualifying events, yet cost recovery remains narrowly confined to politically driven perils—war, terrorism, and nuclear or chemical contamination. Natural catastrophes, floods, earthquakes, and even pandemics trigger only schedule relief, leaving contractors to absorb additional expenses such as standby costs or material price escalations. This asymmetry drives intense negotiation around insurance coverage and bespoke cost‑recovery clauses, especially in regions prone to natural hazards.

Practically, the 2017 changes compel project teams to adopt a disciplined documentation regime from day one of any disruption. Photographs, site diaries, contemporaneous correspondence, and expert assessments become indispensable evidence for both the Engineer’s determination under Sub‑Clause 3.7 and any subsequent dispute resolution. Failure to meet the strict notice and claim timelines can extinguish otherwise valid relief, turning a manageable delay into a financial loss. Consequently, contractors, employers, and engineers must treat exceptional events as a core risk‑management pillar rather than a peripheral contractual footnote.

Force Majeure Under FIDIC: From “Force Majeure” to “Exceptional Events” — What Changed and Why It Matters

Comments

Want to join the conversation?